Difference between revisions of "Simulation/LongTermVariant/hydrology/en"

From Kalypso
Jump to: navigation, search
(Creation of a Long Term Simulation)
(Creation of a Long Term Simulation)
 
Line 16: Line 16:
 
: Here, the latest version should be selected. (Information about the computing core (see: [[Rechenkern/hydrology/de|''Computing Core'']])
 
: Here, the latest version should be selected. (Information about the computing core (see: [[Rechenkern/hydrology/de|''Computing Core'']])
 
; Time series mapping
 
; Time series mapping
: The initially loaded fitting time series must be selected in the respective drop-down menu (Precipitation model, Temperature, Evaporation, Water level or Discharge measurement, Inflow, Open water Evaporation), which was assigned to an [[Zeitreihenzuordnung/hydrology/de|Time Series]] model or a Time Series Mapping using the time series mapping function.  
+
: The initially loaded fitting time series must be selected in the respective drop-down menu (Precipitation model, Temperature, Evaporation, Water level or Discharge measurement, Inflow, Open water Evaporation), which was assigned to a [[Zeitreihenzuordnung/hydrology/de|Time Series]] model or a Time Series Mapping using the time series mapping function.  
  
 
[[Category:Hydrology/en]]
 
[[Category:Hydrology/en]]
 
{{Languages|Simulation/Langzeitrechenvariante/hydrology}}
 
{{Languages|Simulation/Langzeitrechenvariante/hydrology}}

Latest revision as of 22:51, 17 February 2017

[edit] Creation of a Long Term Simulation

First, a calculation model for the long-term simulation has to be applied over several years. The longer the simulation period, the better the significance of the model. The limiting factor here is mostly the data range of the time series, which serve as input time series (Precipitation, Temperature, Evaporation, Inflow Hydrograph). This data should be consistently available and must be linked in the base model.

When creating a new computing variant of a long-term simulation, the control parameters must be specifically defined. Using the button Feature hinzufuegen.png Feature New a new calculation variant can be created. In Feature View the simulation is started with the button with Simulation starten.png :

Description
The created simulation can be renamed via Umbenennen.png.A variation is recommended to define the Long-term Simulation.
Start the Simulation
The start of the simulation must start at 00:00:00 (example: 01.01.1985 00:00:00).
End the Simulation
The end of the simulation must be completed at 00:00:00(example: 31.12.2004 00:00:00). The calculation must run over full years.
Time step
To create a long term simulation specify a time steps of 1440 minutes ( which is equal to 24 hours ).
Version of Kalypso-NA (calculation core)
Here, the latest version should be selected. (Information about the computing core (see: Computing Core)
Time series mapping
The initially loaded fitting time series must be selected in the respective drop-down menu (Precipitation model, Temperature, Evaporation, Water level or Discharge measurement, Inflow, Open water Evaporation), which was assigned to a Time Series model or a Time Series Mapping using the time series mapping function.